COMPLETED December 2020
An aging radio tower on Thunderbird Ridge is being replaced. The tower is a critical piece of public safety infrastructure, providing radio communications for Squamish Fire Rescue, Bylaw and Public Works. It is not used for any high frequency cellular, LTE or 5G services.
The tower is nearing end of life and poses a potential safety risk, especially during wind storms.
Timeframe: November 10 through mid-December.
Impact: The project is divided into two phases:
Phase 1: Tower Foundation (Anchor bolt drilling and concrete pouring)
Timeframe: Tentative start date - November 10; Anticipated duration: 15 working days.
Hours of work: 8 a.m. to 6 p.m.
Phase 2: Tower delivery, assembly and installation plus dismantlement and removal of the old tower.
Timeframe: Tentative start date - November 30; Anticipated duration: 15 working days.
Hours of work: 8 a.m. to 6 p.m.
Impacts:
Questions?
Please contact Jamie McCarthy, Municipal Engineer
jmccarthy@squamish.ca or 604.389.8027
January 6, 2025 at 8:36 PM
MTN Village, Phase 2 - Dewatering
MTN Village, Phase 2, developed by Anthem Centennial Developments LP, is a mixed-use master planned community located ten minutes from…
December 24, 2024 at 8:36 PM
Rainfall Warning Issued for Howe Sound, Squamish
Issued at 2024-12-24 18:49 UTC by Environment Canada:
Rainfall warning issued for:
Howe Sound, B. C.
We use cookies to help improve our website for you.