Brackendale - Government Road Active Transportation Improvements

Details

A separated multi-use path is being constructed along the east side of Government Road between Depot Road and Axen Road. Other improvements to the area will include:

  • Curb extension at Axen Road/Government Road intersection.
  • Drainage and full road reconstruction.

Impacts

  • A detour via Faith Road will be in place from Monday, May 11 to Thursday, May 14 between 7 a.m. and 7 p.m.
  • Signs will be in place to indicate the direction of the detour
  • Faith Road will have a temporary speed limit of 30 km/h.
  • Please use caution, watch for traffic control personnel and obey the 30 km/h speed limit. 
  • Short delays of up to three minutes can be expected.

Timeframe

  • Through May 25, 2020

What's planned

Construction work area

Government Rd 1

Government at Axen

 

April 29, 2020