Brackendale Sewer Trunk Main Replacement

Upgrading of main sewer trunk line from Brackendale is complete.

Timeline (Estimated)

Phase 1   
June 17 to Aug 1: South-end lift station to Eagle Run Drive

Phase 2
Aug 1 to early Sept: Eagle Run Drive to Judd Road

Neighbourhood Impact

Access to businesses along the construction route will remain open throughout the construction (Watershed Grill, Republic Bicycles, Brackendale Bean, The Beehive, The Nest, Howe Sound Dance Academy, Petro Canada, Brackendale Auto Service).

Due to Brackendale’s high water table, dewatering pumps are required to run 24 hours a day during the project to lower the water level and allow work to take place. We recognize this will present noise issues. This is an unavoidable requirement.

Project Details

Traffic Control Plans

The District acknowledges this project will be a disruption to some people. We thank you in advance for your patience, cooperation in planning around the construction, and respecting the work zone as we complete this important work.

Questions can be directed to the District’s Capital Projects Manager - call or email Matt Simmons, 604.815.5000.