June 2023 update: Paving work had begun Tuesday, May 30 through Thursday, June 1 from Tantalus to Diamond Head, followed by the multi-use pathway (Highway 99 to Tantalus). Remaining concrete work at the corner of Tantalus Road and Garibaldi Way and line painting will follow. The project is expected to be completed over the following weeks.
April 2023 update: Work has progressed on schedule with following improvements:
Work will soon begin on improvements to the new Tantalus to one-way (southbound) traffic flow and the relocation of the existing bus stop from Garibaldi Way to the corner of Diamond Head Road.
The remaining work to be scheduled for May includes paving work, 711 second Garibaldi Way access closures, line painting, and streetlight installation.
March 2023 update: Construction will soon begin on a long-planned project to improve the intersection of Garibaldi Way and Tantalus Road. These upgrades are being completed in order to increase safety and improve traffic flow in this area. Work is set to begin in mid-March and continue through until the end of June.
Work will include the installation of a new multi-use path along Garibaldi Way from Highway 99 to Diamond Head Road, a second crosswalk with flashing beacons on Garibaldi Way at Tantalus Road and the conversion of Tantalus Road South to one-way in the southbound direction between Garibaldi Way and Diamond Road.
February 2023 update: Work is scheduled to begin in March and is anticipated to take approximately 10 weeks to complete. Please expect vehicular, cyclist and pedestrian impacts. Affected businesses will be contacted directly.
August 2022 update: The contract has been awarded however due to supply chain issues, they are unable to start work until Spring 2023.
Project Summary
The District of Squamish is working to improve safety and traffic flow for drivers, pedestrians, and cyclists at the intersection of Garibaldi Way and Tantalus Road, as well as the surrounding area.
As part of these safety and traffic flow improvements, the District is planning the following changes:
Construction for these improvements is expected to take place in phases. The initial work is anticipated to begin during the summer and fall of 2022. Please see below for more details on these improvements, and how the District arrived at this design for the intersection.
Project Timeline:
Fall 2020: Community traffic study survey
January 2022: Surveying and preliminary design
March 2022: Information meetings with businesses and residents in the area
March-June 2022: Detailed design
June-July 2022: Tendering and award
August-October 2022: Initial construction expected to begin
Background and Public Engagement:
The need for safety and traffic flow improvements at this intersection has been an ongoing concern. With increasing traffic congestion in the area, combined with numerous reports of near misses and unsafe conditions, the District began a traffic study to identify possible improvements.
As part of this traffic study, a survey was done in the fall of 2020. The goal of the survey was to learn more about how people use the area and what concerns they have with the intersection of Garibaldi Way and Tantalus Road. The survey contained five questions including the participant’s mode of travel, number of times per week using the area, the main purposes of trips, the prime reasons for traveling through this area, and main concerns navigating the area. In addition, participants had the opportunity to provide the details of any near-misses or collisions they experienced or witnessed near the intersection.
The survey received nearly 800 responses from community members. The following items were the main concerns raised from the online survey:
A summary of the survey results can be found here.
A graphic highlighting potential safety issues identified by survey respondents can be found here.
Project Impacts
Tantalus Road South
Tantalus Road South is a lively commercial area with popular restaurants and services. Changing the vehicle traffic flow on the street will create short-term and long-term opportunities to support businesses in the area. Key features that support vibrant commercial areas include adequate sidewalks, attractive green space, and street furnishings that enable gathering and eating outside. These features create a safe and enjoyable experience, attracting visitors to the area.
Good transportation options also support a successful commercial area. Tantalus Road South is located on the frequent transit network and bike network. The upgrades will improve transit and bike access to this area.
Vehicle parking is currently available on private property as well as on the west side of Tantalus Road South and adjacent streets. There are no plans to remove the existing street parking on Tantalus South. Any opportunities to add additional street parking on Tantalus South are very limited due to the number of driveways on the east side of the road. Additionally, a minimum of six metres of open travel width must be maintained for emergency vehicle access on any street.
The District is currently working with businesses on Tantalus Road to understand how these changes may impact them. The District is also seeking input from businesses on how to use the extra roadway width that will be created by removing one lane of traffic to make Tantalus Road South one-way in the southbound direction.
Diamond Head Road
A slight increase in traffic is expected on Diamond Head Road and Diamond Road (between Tantalus Road and Diamond Head Road) due to these changes. The traffic study estimates that during peak hours on Friday and Sunday, between 3:00 - 7:00 p.m., approximately one (0.8-1.2) additional car will travel on these roads per minute.
The areas proposed to have the shoulder widened are highlighted in red below:
What Other Options Were Considered During the Conceptual Design Process?
During the design process, many options were considered to improve safety and traffic flow at the intersection of Garibaldi Way and Tantalus Road. The following possible improvements were considered by Squamish Engineering staff and an engineering consultant during the concept design stage of the project:
Garibaldi Way corridor between Highway 99 and Diamond Head Road:
Garibaldi Way and Tantalus Road Intersection and Approaches:
To determine which improvements provided the most effective solution to the issues in the area, the District reviewed a number of criteria, including:
Using this criteria, it was determined that the most effective solution for the intersection was to convert Tantalus Way South to one-way southbound and combine this with a series of upgrades along the corridor from Diamond Head road to Highway 99 which are listed at the top of this page.
November 13, 2024 at 12:19 AM
Cleveland Avenue between Pemberton and Buckley Avenues will be closed November 14 from 3-11am
CN Rail has informed us that crews will be removing their decommissioned tracks on Cleveland Avenue near Buckley Avenue on…
November 8, 2024 at 2:20 AM
Budget Open House postponed due to Brennan Park power outage
UPDATED: Unfortunately due to a power outage at Brennan Park Recreation Centre on the evening of November 7, the Budget…
We use cookies to help improve our website for you.