Eagle Viewing Area / Siyich'em Reserve Dike Master Plan

Squamish Nation and District of Squamish logos

 

 

Introduction

The District of Squamish completed an Integrated Flood Hazard Management Plan (IFHMP) in 2017 that included over 100 recommendations to manage community flood risk. The IFHMP identified significant deficiencies in the Squamish River dike at the Eagle Viewing Area and Siyich’em Reserve along with unique challenges to complete upgrades including multiple land owners, major infrastructure within and adjacent to the dike and environmental sensitivity. As a result, the IFHMP recommended completing a special study to determine an approach to upgrading the Squamish River dike through this area.

In 2019/2020, the District of Squamish and Squamish Nation developed an Eagle Viewing Area / Siyích'em Reserve Dike Master Plan. The Dike Master Plan documented that the Squamish River dike was constructed on its present alignment in approximately 1968 and did not protect the full extent of Siyich’em Reserve. Siyich’em Reserve has been reduced from its original total area of 68 acres (27 hectares) to 9.8 acres (4 hectares) due to the Squamish River shifting alignment from the west side of the river corridor to its present alignment resulting in significant erosion of reserve lands.

The Dike Master Plan identified, short-listed and provided a concept design for Squamish River dike upgrades to address deficiencies and enhance community flood protection. The master plan also included a public amenity plan and recommended a suite of feasibility-level work to advance the project from the master plan stage to design and construction. Further information on the master plan is available below.

Dike Master Plan - Original Preferred Option

From Siyich’em Reserve to Fisherman’s Park, the original preferred option selected by District of Squamish and Squamish Nation Councils was to re-align the Squamish River dike as shown below in order to re-capture historic reserve land lost due to erosion by the Squamish River.

Map outlining proposed dike and potential land recapture area including both historic reserve land and unceded land.

In the Eagle Viewing Area, the concept design entails raising the existing dike by up to 1.5 m additional height and expanding the footprint towards Government Road, without impacting the road. Depending on the available space between the existing dike and Government Road, the dike upgrading geometry may involve a grass slope with or without an adjacent berm, or a retaining wall.

Pre-Design Study

In 2021, the District and Squamish Nation initiated work on a Pre-Design Study in order to continue advancing the project and implement recommendations of the Dike Master Plan. The scope of work included hydraulic modeling, environmental and geotechnical assessment, engaging with regulatory agencies, and updating the concept design and cost estimates.

Based on technical assessments completed in the Pre-Design Study, substantial implementation issues were identified. It was confirmed that due to environmental impacts associated with re-aligning the dike closer to the Squamish River, the feasibility of re-aligning the dike is contingent on a very large habitat compensation to re-water Pilchuck Creek / Chicken Soup Slough in the upper Squamish Valley. Due to the technical and logistical challenges associated with this enhancement opportunity, the District and Squamish Nation have recognized that a decision in favour of pursuing the enhancement opportunity would not be reached on a timeline compatible with completing urgent dike upgrades.

In late 2024/early 2025, District and Squamish Nation Councils expressed support to re-visit previously short-listed options identified in the Dike Master Plan in tandem with pursuit of offsite opportunities to redress historical decisions and restore useable reserve lands.

Next Steps

Work is scheduled in 2025 to re-visit two previously short-listed options for dike upgrades on Siyich’em Reserve which includes:

  • Option A – Retaining Wall – This option would involve raising the existing dike and minimizing the need for additional space through the use of a vertical retaining wall on the land side of the dike.

Technical diagram of retaining wall with walking path on top.

  • Option B – Land Raising – This option would involve filling the land on Siyich’em Reserve to strengthen the dike and allow raising.

Technical diagram of raised land with walking path on dike crest and existing structure removed and replaced after land raised.

It is possible that the final preferred option may include a hybrid of the above options.

The concept design for upgrading the Squamish River dike through the Eagle Viewing Area is intended to remain the same, however, the design will be refined to minimize in-water work and associated environmental impacts.

Funding

All work undertaken to date on this project has been 100% funded through senior government grants.

Show All

Dike Master Plan: Study Area and Background Information

  • What is the Eagle Viewing Area / Siyích'em Reserve Dike Master Plan?

  • Where is the study area?

  • Why is a dike upgrade needed in this area?

  • When will the dike upgrades be built?

  • What is the project schedule and where are we now?

  • Community engagement

  • Additional Information and Contact Information