Installing a building drainage system?

20180420 091832

Drainage systems for buildings are regulated under the BC Building Code. Historically, 18-inch diameter sump pits have been accepted for buildings regulated under Part 9 of the BC Building Code, however the minimum size of a sump pit for a Part 9 building is 24-inches in diameter. This size is based on a minimum surface area of .25 square metres. 

The District of Squamish Building Department will provide a grace period after which only .6m (24-inch) sumps will be accepted. This grace period will be extended until May 18, 2018.

If you have any questions about your building or project, please contact the District of Squamish Building Department at 604.892.5217.

April 20, 2018

Post your comment

Comments

No one has commented on this page yet.

RSS feed for comments on this page | RSS feed for all comments

We use cookies to help improve our website for you.