Woodfibre LNG Limited is constructing a liquefied natural gas (LNG) export facility on the previous Woodfibre Pulp and Paper Mill site located approximately 7 km west-southwest of Squamish, on the northwestern shoreline of Howe Sound.
The WLNG project is expected to operate for approximately 40 years and includes the development of a natural gas liquefaction facility and an LNG transfer facility to enable the export of the LNG product to global markets via marine vessels. The facility would have a storage capacity of 250,000 cubic metres and a production capacity of 2.1 million tonnes per year of liquefied natural gas.
To supply the WLNG facility with liquified natural gas, Fortis BC Energy Vancouver Island Inc. is constructing an approximately 47 km long 24-inch diameter natural gas pipeline from the area north of the Coquitlam Watershed in the Greater Vancouver Regional District (Metro Vancouver) to the Woodfibre LNG facility, southwest of Squamish; additional compression at existing compressor stations at Eagle Mountain in Coquitlam; a new compressor station in Squamish; and metering facilities at the receipt and delivery points.
September 25, 2024 - TU000073 and TU000074 were considered by Council. TU000073 was defeated and TU000074 was approved. View the September 25 meeting.
View the most recent quarterly report: December 19, 2023 Staff update to Council
View District Q&As about the noise exemption permit.
Two new conditions have been added to the Application:
Condition 31 – Requires FortisBC to develop and implement a gender and cultural safety plan to address the increased risk of adverse effects on women, including Indigenous women and girls
Condition 32 – Requires FortisBC to compel Project workers to reside at the Workforce Accommodation while working on the Project. The Holder may relieve a worker of the requirement based on: the location of the worker’s residence, family, Indigenous or cultural considerations, or reasons acceptable to the EAO. FortisBC must maintain a record of these exemptions, accompanied by a rationale.
View the Amendment Report and Certificate.
View the Fortis BC Environmental Protection Notice ad.
Read the letter to Council.
Public comments can be directed to [email protected] and [email protected]. More details on the project and water management can be found at talkingenergy.ca/egp
As a requirement of WLNG’s BCER facility permit, on August 9, 2024, WLNG issued a Notice of Construction to the District of Squamish relation to marine facility construction. Construction activities are further described on WLNG’s website. August Construction Update | Woodfibre LNG
As a requirement of WLNG’s BCER facility permit, on July 29, 2024, WLNG issued a Notice of Construction to the District of Squamish relating to the construction of the LNG facility. Construction activities are further described on WLNG’s website. August Construction Update | Woodfibre LNG
On June 2, 2023, WLNG issued its 90-day construction notice to the BC Environmental Assessment Office (EAO). Various permits and agreements are still required for stages of construction as described in the schedule.
Milestone | Forecasted Date |
Site Preparation | September 1, 2023 |
Start of Rough Grading | November 14, 2023 |
Start of Outside Battery Limits Construction on Site | February 13, 2024 |
Start of Inside Battery Limits Construction on Site | August 14, 2024 |
First Module Arrive at Site | October 8, 2024 |
Complete Material Offloading Facility (MOF) Installation | December 20, 2024 |
On July 28, 2023, FortisBC issued its 30-day construction notice to the BC EAO with the intent of commencing construction activities on August 28, 2023. Various permits and agreements are still required for stages of construction as described in the schedule.
EGP Project Component | Construction Start |
Initial Construction Activities | Q3 2023 to Q1 2024 |
EGP Tunnel Portals Construction | Q3 2023 to Q4 2023 |
EGP Tunnel Construction | Q4 2023 to Q3 2026 |
Squamish Compressor Station Construction | Q1 2024 to Q3 2025 |
EGP Pipeline Construction | Q2 2024 to Q4 2026 |
EGP Pipeline Twinning Construction in Coquitlam | Q1 2024 to Q3 2024 |
Eagle Mountain Compressor Station | Q1 2024 to Q3 2025 |
The WLNG and EGP projects are regulated by local, Indigenous, provincial, and federal governments and related agencies, including the BC Energy Regulator (BCER) and the National Energy Board (NEB).
Regulatory Process and Responsibilities
Regulatory responsibility for oil and gas activities in British Columbia is delegated to the BC Energy Regulator (BCER) (formerly the BC Oil and Gas Commission) through the Energy Resources Activities Act, which is BC’s regulatory framework for all oil and gas activities in the province. The BCER is an independent, single-window regulator for the natural gas industry, overseeing exploration and development, pipeline transportation, LNG facilities, and reclamation.
LNG facilities and oil and gas activities are also required to undergo an Environmental Assessment in BC, which is administered by the Environmental Assessment Office, and governed by the Environmental Assessment Act.
While WLNG and FortisBC are required to consult with the District of Squamish on various management plans and technical reports as outlined in Environmental Assessment Certificate Conditions, the District does NOT have approval authority over such plans or reports.
Further information is provided below on the regulatory processes and the different Provincial and District responsibilities with respect to the WLNG facility and pipeline projects.
In BC, permits to construct and operate an LNG facility (that does not cross provincial borders) are required from the BCER before construction can begin. Applicants must provide the BCER with detailed project descriptions, construction schedules, design and safety studies and risk assessments demonstrating how they meet or exceed levels of protection as outlined in regulation. The BCER’s role is to ensure plans meet all applicable requirements in the Liquefied Natural Gas Facility Regulation and any associated Energy Resource Activities Act approvals meet specific conditions in order to be in compliance with their permit, if approved. These are legally-binding conditions the company must implement to remain in compliance and ensure environmental impacts are mitigated.
LNG facilities are required to undergo an environmental assessment in B.C. The Environmental Assessment Office follows a clearly defined process in the Environmental Assessment Act to conduct these assessments. This process, including reports and consultation details, is available to the public on the Environmental Assessment Office’s project site (EPIC).
Section 22 of the Environmental Assessment Act establishes a requirement for consultation and notification before applications for oil and gas activity permits can be submitted.
WLNG’s Environmental Assessment Certificate (EAC), issued by BC’s Environmental Assessment Office (EAO), includes several conditions WLNG must meet at various project stages.
The BCER provides regulatory oversight for oil and gas pipeline transportation, including the construction, operation and maintenance of the pipeline. Regulatory staff have the legislative authority to make decisions on proposed oil and gas activities. In addition, the Regulator:
Once complete, an oil and gas activity application is submitted to the Regulator for review. The Regulator conducts a wide range of technical reviews during the review and determination process, which include engineering (facilities, pipelines or drilling and production), land and habitat, forestry, agriculture, archaeology and environmental management. During the review and determination process, the Regulator also conducts a wide range of engagement processes, liaising with First Nations, stakeholders, landowners and partner agencies. If the Regulator finds minor and/or major deficiencies, the Regulator contacts the applicant to clarify details, make revisions and/or provide additional information.
Similar to WLNG, FortisBC’s EGP project is also regulated by the EAO through its Environmental Assessment Certificate and must meet conditions in its EAC.
Permit holders must submit an amendment application to add, modify or change any permitted oil and gas activity and/or associated oil and gas activity. An amendment can include requests for multiple changes to a permit. The Regulator will consider only one amendment application per permit at a time.
Once a permit is issued, permit holders are responsible for all permit holder obligations, including outcomes of actions of contracted personnel in carrying out permitted oil and gas activities on behalf of the company.
The permit holder must submit a notice of construction start to the Regulator prior to the start of construction activities.
Under Section 26 of the Energy Resources Activities Act, the Regulator has the authority to refuse, suspend, cancel, or amend a permit.
Legislation empowers, guides, limits, and affects local governments. BC’s Community Charter (CC) and the Local Government Act (LGA) define the core authority of local governments and guide decision-making. As part of its powers and responsibilities defined by the LGA and CC, the District of Squamish regulates land use and development within District boundaries.
The District’s role as a regulator for the WLNG and Fortis projects is guided by the LGA and CC and includes the issuance of development-related permits and work permits associated with the construction and development activities for the projects.
In addition to permits issuance, the District has legislative authority to enter into various agreements to offset associated economic, environmental, and social impacts arising from projects. Forms of agreements can include Service Agreements, Revitalization Tax Exemption Agreements, and Community Benefit Agreements.
While WLNG and FortisBC are required to consult with the District of Squamish on various management plans and technical reports as outlined in EAC Conditions, the District does NOT have approval authority over such plans or reports.
The number and nature of local permits and agreements are subject to construction plans submitted by WLNG and FortisBC. Approved building permits for each project are available through the District’s Open Data platform while the District’s Development Showcase provides an overview of all active Development Permit Applications, including Temporary Use Permits relating to the WLNG and FortisBC EGP project.
View an overview of permits applied for.
Please refer to the regulator websites below for more information on regulatory approvals and supporting documentation for the WLNG Project.
Please refer to the regulator websites below for more information on regulatory approvals and supporting documentation for the FortisBC EGP Project.