October 2023 Update:
The construction schedule has been extended until December 2023. This project has experienced delays due to long material lead times, challenging ground conditions, the presence of conflicting third party utilities that needed to be relocated, and additional repairs required inside the lift station to ensure it can be safely be brought back into operation.
Progress to-date:
Construction is underway at Queens Way Lift Station to replace the inlet manhole that collapsed on January 14, 2023. Work consists of bypassing the lift station, sheet piling, excavation and dewatering to a depth of 6 metres below the surface, subgrade preparation, installation of two new inlet manholes to replace the collapsed manhole, backfill, commissioning of new infrastructure and restoration work.
Project Timeline: Construction is currently underway and now is expected to be complete in November 2023.
Impacts: Traffic control measures are currently in place with modified traffic flow on Queens Way and a 30km/hr construction zone speed enforced. Access to Pioneer Way will be closed to all non-local traffic for the duration of the project. The public is advised to take extra caution when travelling down Queens Way due to higher congestion around the construction areas. Please obey all posted traffic control signs.
March 10, 2023
June 26, 2024 at 3:01 PM
Hours of Operation - Monday, July 1, 2024
Please note the following operating hours for Canada Day - Monday, July 1.
June 13, 2024 at 5:51 PM
Recycle BC Update: New Depot in Squamish Delays
Recycle BC has posted the following news release to their website:
We have an important update for Squamish residents regarding the…
We use cookies to help improve our website for you.
Post your comment
Comments
No one has commented on this page yet.
RSS feed for comments on this page | RSS feed for all comments