October 2024 Update:
Queensway Lift Sation project is complete. The station and new receiving maintenance hole were successfully commissioned and back in operation since March 2024.
The station was bypassed, for more than a year, to facilitate the replacement of the maintenance hole that collapsed back in January 2023. While the station was offline it was thoroughly inspected, so the internal condition could be fully assessed. Additional repairs were required to safely bring the station back into operation, including replacement of the internal piping and valves, relining the wet well, and replacement of all grating and support beams. These improvements will ensure a safe and fully functional lift station, now and into the future.
Some site restoration activities are outstanding including re-instatement of fire hydrant, street lighting, and multi-use pathway, which will be completed by November 2024.
October 2023 Update:
The construction schedule has been extended until December 2023. This project has experienced delays due to long material lead times, challenging ground conditions, the presence of conflicting third party utilities that needed to be relocated, and additional repairs required inside the lift station to ensure it can be safely be brought back into operation.
Progress to-date:
Construction is underway at Queens Way Lift Station to replace the inlet manhole that collapsed on January 14, 2023. Work consists of bypassing the lift station, sheet piling, excavation and dewatering to a depth of 6 metres below the surface, subgrade preparation, installation of two new inlet manholes to replace the collapsed manhole, backfill, commissioning of new infrastructure and restoration work.
Project Timeline: Construction is currently underway and now is expected to be complete in November 2023.
Impacts: Traffic control measures are currently in place with modified traffic flow on Queens Way and a 30km/hr construction zone speed enforced. Access to Pioneer Way will be closed to all non-local traffic for the duration of the project. The public is advised to take extra caution when travelling down Queens Way due to higher congestion around the construction areas. Please obey all posted traffic control signs.
March 10, 2023
December 14, 2024 at 5:36 PM
Highway 99 closed at Lions Bay due to landslide
Highway 99 is currently closed in both directions due to a landslide which occurred earlier today between Lions Bay Avenue…
December 13, 2024 at 4:50 PM
Holiday Hours - December 21 to January 2
Please note the following exceptions to regular hours of operation during the holiday season
Location
Date
Hours
Municipal Hall
December 23 to December 27
Closed
January 1
Closed
Community…
We use cookies to help improve our website for you.
Post your comment
Comments
No one has commented on this page yet.
RSS feed for comments on this page | RSS feed for all comments