Annual Watermain Replacement

Work completed December 4, 2018.


Four waterlines are being replaced and upgraded this year as part of the District’s annual watermain replacement program:

  • Skyline Drive (short, bottom section only) - Scheduled for September 24 to November 5
  • Agryle Crescent - Scheduled for November 5 to 19
  • Garibaldi Crescent - Construction underway; estimated completion date: October 1
  • Clark Road - Watermain replacement complete; repaving expected to begin late September

Traffic impact: There will be some traffic impacts to nearby residents. Some residential water supplies will be temporarily disrupted as individual homes are connected to the new waterline. Door notices will be delivered to affected residents prior to any disruption.

Timeframe: Early August into the fall

Questions? Please contact Jon Allan, Engineering Technician at
604.848.4842 or by email here.  